Revision Sequence Checking
- Damith Samarakoon
- Rebecca David
- Former user (Deleted)
What is Revision Sequence Checking?
The Revision Sequence checking feature helps Document Controllers ensure that project members do not mistakenly supersede Documents with revisions that are out of sequence.
This feature works differently if you have Automatic Numbering switched on. If you upload a revision that is previous to the current revision then it will upload to the background and does not give a warning.Â
Turn On Revision Sequence Checking
To turn on Sequence checking;
1. Go to Configure.
2. Modules.
3. Publication Space.
4. Click on the numbering tab.
5. Select Enable.
6. Select an option from the drop down list.
What is the Difference Between "A-ZZ then 0-99" and "0-99 then A-ZZ"?
A-ZZ then 0-99
Selecting this option means that the Rev sequence check starts at A and matches all the way up to  ZZ and then from 0 to 99.
0-99 then A-ZZ
Selecting this option means that the Rev sequence check starts at 0 and matches all the way up to 99 and then A to ZZ.
What is A.1 ... to A-Z then 0.1 ... 99 to 0-999?
Selecting this options means that A.1 is considered a lower revision than A followed by 0.1 and then 1,2 and so on.
This is an example revision sequence that will match this option.
A.1
A.2
A.3
A
B.1
B.2
B.3
B
0.1
0.2
1
Who Can Turn This Feature On?
You need to be a Project Administrator to be able to access the page to enable this feature.
Refer here for how this feature works.