Pre-Approval of Tender Packages
There are a number of pre-approval options that you can configure for Tender Packages.Â
1. Go to Tender Project Settings.
2. Click on the Package Config tab in the Wizard.
Pre-Approval Form
Configure this option if your procurement process requires you to obtain Approval prior to Issuing the Tender Package.
1. Select Enable the Pre Approval Form.
2. This then allows you to select an RIB cx form that you can use for the Approval process.
3. With this option configured you can create a new package but cannot issue it until the Approval form has been Closed.
4. When you come to the last step in the process of creating a package. The Issue button is disabled. Instead the Request Approval Button is shown.
5. When this is clicked it will load a new Form of the configured form type in Step 2.
6. Once this form is in a Closed Status the Issue button will be enabled.
If you tick the cannot create package through create button, the create Package Button will be disabled.Â
Requires Package Approval
Configure this option if a package can only be created once the approval process is complete.
The difference between this config option and the Pre-Approval Form option is that you can cannot create a tender package until approval has been received.
Configure Approval Form type
1. To set this process up, Select enabled.
2. Then select the Form type to use used for the Approval process.
Configure Create Package Toolbar Option
Once you have done this go to this Forms Configuration Page and enable the Create Package Button in the toolbar. To do this go to.
1. Configure.
2. Document types.
3. Select the relevant document type.