Linked Budget Drop Down on Contracts, Variations and Forecasts

Linked Budget Drop Down on Contracts, Variations and Forecasts

Sometimes referred to as Complex Commitments.  When enabled, the linked budget drop down field will show when creating, editing or approving Contracts, Variations and Forecasts.  

Budget 

Refer Here for how to Create a Budget.

Screenshot of a single budget with two parent rows (Building A and Building B) with the trades for each displayed underneath.  For example the Civil Trade has been created for both Building A and B.

Contract

When creating a contract, the Linked Budget Line dropdown will be available.  For each row select the budget line the row is to be linked to in the budget.

Variation

When a variation is submitted from a Subcontractor for approval, the Linked Budget Line dropdown will be available. For each row select the budget line the row is to be linked to in the budget.

Claims

When a Claim is submitted by the subcontractor line items including variations can be shown as collapsed or expanded to view all line items.

Control Sheet

When looking at the Control Sheet the two linked budget lines are displayed separately.

When the config option is set to Linked Budget, the budget amounts are a Sum of any matching line items on contracts linked to this budget line.

  1. Contract Amount

  2. Contract Variations Pending

  3. Contract Variations Approved

  4. Uncommitted Works

  5. Claims Pending

  6. Claims Approved

Example Contract

Example 'Certified to Date' Amount

If a variation has multiple linked budget lines, 'Certified to Date' Amount is displayed once in Control Sheets for variations with multiple BGT lines

Example Variation

Example Forecasts

Budget Figures Recalculated

When updating or adding amounts to the budget line, these figures will also be recalculated:

  1. Contract Committed To Date

  2. Forecast Cost to Complete

  3. Variance To Estimate

  4. Percentage Completed

  5. Also, recalculate the numbers on all sub-header and header rows.

The Budget Line History page reflects all the updated recalculations.

Related content

Create a Variation from a Contract Line Item(s) in a Budget
Create a Variation from a Contract Line Item(s) in a Budget
More like this
Create a Budget
Create a Budget
Read with this
Budget Configuration
Budget Configuration
More like this
Budget Line Activity History
Budget Line Activity History
Read with this
Contact Variation - Show Linked Budget Line Column
Contact Variation - Show Linked Budget Line Column
More like this
Approve a Claim
Approve a Claim
Read with this