Linked Budget Drop Down on Contracts, Variations and Forecasts
Sometimes referred to as Complex Commitments. When enabled, the linked budget drop down field will show when creating, editing or approving Contracts, Variations and Forecasts.
Budget
Refer Here for how to Create a Budget.
Screenshot of a single budget with two parent rows (Building A and Building B) with the trades for each displayed underneath. For example the Civil Trade has been created for both Building A and B.
Contract
When creating a contract, the Linked Budget Line dropdown will be available. For each row select the budget line the row is to be linked to in the budget.
Variation
When a variation is submitted from a Subcontractor for approval, the Linked Budget Line dropdown will be available. For each row select the budget line the row is to be linked to in the budget.
Claims
When a Claim is submitted by the subcontractor line items including variations can be shown as collapsed or expanded to view all line items.
Control Sheet
When looking at the Control Sheet the two linked budget lines are displayed separately.
When the config option is set to Linked Budget, the budget amounts are a Sum of any matching line items on contracts linked to this budget line.
Contract Amount
Contract Variations Pending
Contract Variations Approved
Uncommitted Works
Claims Pending
Claims Approved
Example Contract
Example 'Certified to Date' Amount
If a variation has multiple linked budget lines, 'Certified to Date' Amount is displayed once in Control Sheets for variations with multiple BGT lines
Example Variation
Example Forecasts
Budget Figures Recalculated
When updating or adding amounts to the budget line, these figures will also be recalculated:
Contract Committed To Date
Forecast Cost to Complete
Variance To Estimate
Percentage Completed
Also, recalculate the numbers on all sub-header and header rows.