Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Next »

Forecasts allow you add a prediction of an additional cost not associated with a contract variation. A forecast record will display on the budget in the Uncommitted Works column and is included in the Forecast Cost to Complete. They can remain in the budget until no longer require or the cost becomes a variation.

Adding a Forecast

  1. Select the budget
  2. Click on the line item to bring up the Line item history
  3. Click Forecast in the toolbar
  4. Enter a Title describing the forecast issue.
  5. Address the forecast. This will give others access to this Forecast record
  6. Enter the item's new Description, Quantity and Rate. You may insert additional lines and indent sub-items as needed.
  7. Click Submit

Removing a Forecast

To remove a forecast from a budget, the status type must be CLOSED.

  1. Select the Forecast you want to remove from either the budget history or the Forecast register
  2. Click Respond
  3. Change the Status to Closed
  4. Click Submit

 The amount of the forecast will be removed from the budget. The forecast will remain in the budget history and the forecast register for audit history.


  • No labels