From June 2019, there There are a number of new pre-approval options that you can configure for Tender Packages prior to Issuing Packages to support Pre-Package Approval processes.
1. Go to Tender Project Settings.
The
2. Click on the Package Config tab in the Wizard is a new Configuration option that allows you to turn on and off a number of features.
Pre-Approval Form
If your Procurement Configure this option if your procurement process requires you to obtain Approval prior to Issuing the Tender Package then this option allows you to configure this approval process.
1. Select Enable the Pre Approval Form.
2. This then allows you to select an iTWOcx RIB cx form that you can use for the Approval process.
3. With this option configured you can create a new package but cannot issue it until the Approval form has been Closed.
...
6. Once this form is in a Closed Status the Issue button will be enabled.
If you tick the Cannot cannot create package through create button, the create Package Button will be disabled.
Requires Package Approval
If Configure this option if a package can only be created once the approval process is completed, then this configuration option will allow you to set up this process. complete.
The difference between this config option and the Pre-Approval Form option is that in the previous setting, you can cannot create the package and then request approval before Issuing it.With this option turned on you must complete the Approval Process prior to even being able to Create the packagea tender package until approval has been received.
Configure Approval Form type
1. To set this process up, Select enabled.
2. Then select the Form type to use used for the Approval process.
Configure Create Package Toolbar Option
Once you have done this go to this Forms Configuration Page and enable the Create Package Button in the toolbar. To do this go to.
...
4. Tick the Add a button to Create a Tender Package to the Tool bar option.