Occasionally you may need to modify the amounts for a Budget line item. This is a achieved with a Budget Variation.
To create a budget variation
1. Click on the budget line you want to add the variation to.
...
3. Give the variation a descriptive Title.
4. If there is an approval process select Pending Approval as the status.
...
7. Repeat until all line items are added.
8. Click submit.
Linked Budget Line option
If checked, the variation will display an extra column to a variation which allows headings / rows to select a budget line item from a drop down.
Then when using the allocate to budget utility, it will default based on these selected lines.
...
.
...
Info |
---|
Variations will show in the Proposed adjustments column until approved, whereby they will move to the approved adjustments column. |
...