Overview
The quality workflow starts with the creation of an ITP.
...
Action Points, Survey and Test Requests are all split from the Lot form.
Let's Get Started
1. Click the plus icon (+) on Project Toolbar to open the 'Create New Document' window.
...
3. The new ITP window will display. Depending on your project set up the ITP may be addressed to the person responsible for approving it via distribution rule. If not, address to the relevant person.
...
7. Once you have added all the ITP tasks, click Submit to issue the document.
Add Row
Anchor | ||||
---|---|---|---|---|
|
1. Click Add Row to access the ITP Task bar.
...
Note |
---|
Task fields may be adjusted to support your workflow. |
lmport form Clipboard
1. Prepare your excel spreadsheet using the titles shown in the ITP Task bar as the titles for your columns.
...