Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

OptionsDescription
NoneNone applied.
Original Contract SumRetention is based on the original contract amount
Adjusted Contract SumRetention is based on the original contract amount plus all approved variations
Bank Guarantee

If selected

a percentage is withheld until specified dates

you'll be able to enter the percentage guaranteed and report on the milestone dates
Does not affect the claim

Practical Completion released %Percentage of retained sum for Practical completion
Final Completion releasedPercentage of retained sum for Final completion
Retention fundIf selected a percentage of payment is withheld from certified claims
Retention per claimThe percentage of the claim that is withheld
To MaxThe upper limit of the retention fund as expressed as a percentage of the contract.

...