In this release we have implemented the following feature

Tenders

Ability to extend the number of days a package is active (after the package closed date)


With this release, you can customise how many days after the package close date the bidder can access the bidder page/portal

The default is 90 days. 

You will need to be a r to configure this

And the tender package must not be set to enforce the close date 


You can customise this by;

  1. Going to Configure > Modules > Tenders > Project Details tab
  2. Change the Bidder Portal days and save