The Defects Manager Dashboard clearly identifies when rectification works have been completed by the subcontractor and works are ready to inspect. This makes scheduling of inspections and sign off on defects easy.

Inspecting the Defect

1. Access the Defects Dashboard by clicking on Defects in the menu.

Image RemovedImage Added

 2 2. Click on the widget Defects to Inspect.

Image RemovedImage Added

This will list all defects that require inspection.

Image RemovedImage Added

3. To view the defect form, simply click on the reference number.

Image RemovedImage Added

4. After inspection or review of the updated defect form, the Defect Manager has the option to Pass or Fail the rectification works.

...

Resolving the Defect

To pass the defects, simply click on the Pass button.

Image RemovedImage Added

This will change the status of the document form to Rectified RECTIFIED and close the defect is now closed.

Image RemovedImage Added 

...

When Work is Not Completed

To Fail the defect, simply click on the Fail button. 

Image RemovedImage Added 

This will change the status of the document form to ISSUED FOR REPAIR and returns it to the subcontractor for re-work.

Image RemovedImage Added 

This cycle continues until the defect repair is deemed to be Rectified by the Defect Manager.

...