This option is found on the Claim forms.  

When selected the:

  • Retention amount will include these rows.
  • Total value of the contract will include retention for these rows.

1.

...

 This can be accessed under 'Form Types' → Contract Progress Claim → Contract Admin tab.

2. Choose which type of claim you want to add this option to.

...

Image Added

3. Scroll down on the right hand side pane until you see:

Image Added

Retention Cap Calculations

You have the configuration option to claim. This can be accessed under 'Form Types' → Contract Progress Claim → Contract Admin tab.

Retention Calculation method for unapproved variations on account has 2 options:

Options available

  1. Variation Amount (default / current)

  2. Claimed / Scheduled Amount


Image Added

Applicable Variations: Claimable Variations on Account, in an open status (not draft / withdrawn / approved).

Claimed / Scheduled Amount :

If this setting is set to "Claimed / Scheduled Amount", for applicable variations, we calculate the retention based on the amount that is being claimed (for the author) or the scheduled / certified amount for the approver (CA Project Admin).

If a variation moves from Open (unapproved) to Closed (Approved)

  1. While the claim is not yet approved: it will update the retention calculation and be treated the same as other Approved Variations.

  2. After the claim is approved:

...

  1. it will not affect the current claim, however, will be considered as an approved variation in the next claim raised against that contract.