Generate a Handover Report
...
2. This will launch a pop up showing you the different options for your report.
The Elements of the Handover Report
...
4. Tick whether you want to include the attachment of the related document types.
Including Second Level Documents
Anchor | ||||
---|---|---|---|---|
|
If you would like to include the documents linked at a secondary level please tick the Include second level linked documents tick box.
In the example below the work lot has an Action Point, Inspection and Test Plan (ITP) and a Test Request as related documents.
...
This will download the report as a zip file.
What the Handover Report Zip File Looks Like
...
1. Click on Send on a Form.
2. This will generate the report as a zip file.
...
4. In this example the General Correspondence has been selected.
5. The new General Correspondence form is created with the zip file attached to the form.
6. Fill in the title, action and info collaborators as well a comment and click submit. The form will be sent.