Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Before using the iTWOcx Before using the iTWO cx Quality Module, you will need to configure / confirm the following form options.Image Removed Confirm

  • Confirm the layout of the quality forms is suitable to the project.

...

  • Confirm the authors of the quality forms.

...

  • Confirm statuses and status allocations.

...

  • Confirm the closers of the documents.

...

  • Configure the project specific data for each of the forms.

General Configuration

When setting up the Quality forms, consideration should be given to whether any changes to default settings are required for the following:Image Removed

  • Authors - Who can create this document?

...

  • Numbering -

...

  • Do you want sequential numbering or do you require any special fields to display?

...

  • Title and Due Date - Who can edit these on a submitted document.

...

  • Closers & Status

...

  • Changes - Depending on the workflow of Quality on the project who is allowed to change the status of a document.  Particular consideration should be given to closers.

Image RemovedImage Added

Statuses

Statuses help to define the workflow of iTWOcx iTWO cx forms.  Default statuses are set for each QA Form type, however, these can be configured to reflect the quality workflow on your project.

Consideration should be given to Status options and who has access to each of them. 

Image RemovedImage Added

User Fields

The Quality forms contain forms contain a number of user fields.  Some of these fields appear fields appear on all of the quality forms.  Where select or cascading fields appear fields appear on multiple forms, the options must be added to each oneform.

Note

To learn more about adding user field options click here.

ITP Form

The default layout for the ITP is shown below. 

Image RemovedImage Added

It contains a number of text user fields and a select field for Construction Processfields.

Options for Construction Process will the Select user fields need to be added to support project workflow.  This field also appears on other QA forms and as such, options must be added to all forms.

Image RemovedImage Added

The ITP also contains a table for tasks.  Tasks are populated by text user fields for the following items:

Image Modified Item No;

Image Modified Task, Frequency.

Image Modified Applicable Standard.

Image Modified Method, Acceptance Criteria.

Image Modified Action.

Image Modified Responsibility.

Options may vary to those shown above where project customisation has occurred.

Lot Form

The default layout for the LOT is shown below. 

Image Modified

The LOT contains two main sections;

Image Modified Lot Specification information; and

Image Modified ITP information which is populated directly from the ITP when splitting.

The default user fields relating to Lot information are shown below:

Image Modified Zone;

Image Modified WBS (Work breakdown Structure).

Image Modified Discipline.

Image Modified Chainage From/To.

Image Modified Location details.

These options can be modified to support project workflow. The ones shown below are select fields and will require project options added. Where these fields are on other forms, the options will need to be added to each.


Ability to create as many custom split buttons as required

In the form, configuration click on the new Custom Split Button

To add a new custom split button click on Manage Custom Splits button under the form type configuration.

Image Modified

The in the new pop up window you can click on the "Add New Button" to create a new Button

Image Modified

Give the button a name

...

After adding the row and settings the options as needed click save on the row to create this custom split button

Image Modified


To edit a buttons details, you can click the edit button

Image Modified

You can retire the split buttons by clicking on the Retire button on the row

Image Modified

Action Point

The default layout for the Action Point is shown below. 

Image Modified

The Action Point is used to manage Hold Points, Inspection Points and Witness points. The user field for Record type is used to make your selection.

The form itself contains fields that are prepopulated from the ITP and the LOT. Where select or cascading options are added on these forms this must also be added to the Action.

The Schedule Section uses date select fields to add time and date information. These are set by default and no additional configuration is required to this section.

Survey Request

The default layout for the Survey Request is shown below. 

Image Modified

The Survey Request form contains a user field for Survey Type. Edit the field options to customise options relevant to your project.

Image Modified

The form also contains fields that are prepopulated from the ITP and the LOT. Where select or cascading options are added on these forms these must also be added to the Survey Request.

The Schedule Section uses date select fields to add time and date information. No additional configuration is required for this section.

Test Request

The default layout for the Test Request is shown below. 

 Image Modified

The Test Request contains 3 sections;

Image Modified ITP and Lot details;

Image Modified Test Request Details; and

Image Modified Test Schedule.

The ITP and Lot section will populate from the Lot form. Where select or cascading options are added on these forms these must also be added to the Test Request.

The Test Request section has a number of text user fields and also contains a TEST TYPE which will need to have options added to make it project specific.

Image Modified

The Schedule Section uses date select fields to add time and date information. No additional configuration is required for this section.

Non-

...

conformance Report

As with all QA documents, the NCR contains user fields populated from the Lot. All select and cascading field options must be added the NCR form.

Image Modified

The NCR has sections that display options detailing the Nonconformance, the Proposed Action and the cause. Default options are available but may need customisation for use on your project. 

Image Modified

History for forms via in-line split from a document list user field

When you split from a document list user field, the form history will now record which row in the table you split from

Image Modified

Handover Report Summary

We’ve added a new Summary report when generating a handover report, so that you may easily identify what forms are going to be included in the report – PRIOR – to downloading it. The report content and data will update based on the selections you make.

Image Modified